An extension is often the quickest way to add production or storage space without relocating. Joining new steelwork to an existing building is a different job from building on a clear site, because the existing structure dictates much of the design.

Do you need planning permission?

In England, some extensions to industrial and warehouse buildings fall under permitted development (Class H of the General Permitted Development Order). The headline limits are an increase of no more than 50% of the original floor space or 1,000 m², whichever is less; no part within 5 m of the site boundary; and no higher than the existing building. Tighter limits apply in conservation areas and other protected land, and parking or turning space can’t be lost. Always confirm with your local planning authority. Permitted development also doesn’t remove the need for Building Regulations approval.

Will the existing building take the extra load?

This is the question most often missed. Where a new roof meets an existing one, snow can drift and pile up against the higher roof, creating much heavier local loads than the original designer allowed for. Valleys, parapets and level changes all need checking. If the extension is attached to the existing frame, the existing columns, rafters and bracing may also pick up new loads.

So the engineer needs to check the existing structure as well as design the new one.

What do you know about the existing frame?

Original drawings and calculations are often lost. A measured survey of member sizes, connections, bracing and condition is the starting point. Corrosion, earlier alterations and missing bracing are all common in older buildings.

Foundations next to existing ones

New foundations must not undermine existing ones. Excavating alongside old pad foundations needs care, and differential settlement between old and new can crack floors and cladding junctions. A movement joint is often the answer.

Fire, weather and the junction

The junction between old and new is where problems show up: leaks at the flashing, gaps in fire separation, and cladding that doesn’t line up. Detail it properly at design stage rather than on site.

Working next to a live operation

Most extensions are built while the business keeps running. That means planned segregation, safe crane lifts away from staff and stock, and clear communication with the site team every day. Under CDM 2015, this belongs in the construction phase plan.

How we approach extensions

ReviveLogix surveys and checks the existing structure first, then designs the extension around it. That way the old and new parts are designed to work together, including under snow load. You can read more about our extensions and modifications work.